Typical Installation
District Heating Plant
London, Ontario, Canada
Project Description: One (1) MCU 30
with back pressure steam turbine
Site Rating:
3,500 kW (average plant electrical load)
30,000
pounds per hour (average plant steam load)
Performance:
98% (average operating reliability)
96% (average
availability)
Cardboard/Paper Manufacturing Plant
Tequisquiapan, Queretaro, Mexico
Project Configuration: Three (3) MCU 30s with back
pressure steam turbine; natural gas, no steam injection
Site Rating:
10,000 kW (average plant electrical load)
83,000 pounds per
hour (average plant steam load)
Performance: 99%
(average operating reliability)
99% (average
availability)
Home Page Introduction MCU PGU Installations Fabrication PDI Contacts Links